Kwai Chung Container Port Terminal 7 Development


This project involved laying approx 155,000 tonnes of Granular Sub Base Type 1. The total tonnage of asphalt laid was approx 70,000 tonnes.


Kwai Chung Container Port Terminal 8 Development


This project involved laying approx 456,000 tonnes of Granular Sub Base Type 1. The total tonnage of asphalt laid was approx 153,000 tonnes.