Project - Container Terminals
Freeport Container Port, Bahamas
Total Tonnage | : 11,000 tonnes |
Project Type | : Pavement works |
Contract Duration | : 3 months |
pin_drop Google Map
Anderson Asphalt completed the laying of over 11,000 tonnes of asphalt overlay to the extension of the Freeport Container Terminal in the Bahamas within a 3 month period. Mixing the Asphalt in its own 160 tonnes per hour plant and laying it with pavers imported from Hong Kong and Philippines.