Airport Runway Re-surfacing Project in
Bahamas
Anderson
Asphalt (Bahamas) Limited [A subsidiary of Anderson Asphalt
Limited] completed the pavement resurfacing of the Grand Bahama
International Airport runway resurfacing in the middle of
2002.
Background information of the project
is summarized below:
- The total length of the runway : 11,200 ft
- Estimate tonnage : 25,000 MT
- Works were undertaken under both displaced thresholds
and night closure conditions.
- Construction time: 2 months
- Aircraft landing and depart per day: around 200
- Output of the mixing plant: 160 MT per hour
- 3/4 inch mix and 1/2 inch mix are used on this runway
project to ICAO and FDOT standards. Computerized level control
was used for laying works.
- Laying temperature between 140oC to 160oC
- Thickness variation 34mm-75mm
Major
equipment for the project :
- ACP RM2000 Mobile Asphalt Plant
- Wirtgen 2000DC Milling Machine
- ABG Titan 325 Paver Finisher
- Paveset Grade Control
- Volvo L120D Wheeled Loader
- CAT 936F Wheeled Loader
- Hamm DV8.42S Vibratory Roller
- Hamm DV2 Vibratory Roller
- Dynapac CP202W Tyred Roller
- Johnston 600 Suction Sweeper
- Cummns 750KVA Sllenced Genset
- Massenza 4000l Truck-mounted Sprayer
- Atlas Copco XAS75Db Air Compressor
- Mobile Workshop
|